ISM, ISMe, and QSM11 – 011-042   Aftertreatment Fuel Injector

Table of Contents

Inspect for Reuse
Install

Inspect for Reuse

TOC

Attach the heat shield to the injector.

Install a new high temperature EZ tie to hold the injector harness to the heat shield.

Install a new fibrous insulator.

Install a new metal gasket.

NOTE: The fibrous insulator will be against the injector.

Install the aftertreatment injector onto the adapter pipe.

Apply a coat of high temperature anti-seize compound to the capscrews.

Install the capscrews and spacers.

Torque Value:  14  n.m  [124 in-lb]

SMALL | MEDIUM | LARGE

Install

TOC

Attach the heat shield to the injector.

Install a new high temperature EZ tie to hold the injector harness to the heat shield.

Install a new fibrous insulator.

Install a new metal gasket.

NOTE: The fibrous insulator will be against the injector.

Install the aftertreatment injector onto the adapter pipe.

Apply a coat of high temperature anti-seize compound to the capscrews.

Install the capscrews and spacers.

Torque Value:  14  n.m  [124 in-lb]